MRP
MRP – the calculation that decides what a factory orders, and when
MRP explained from the ground up: why component requirements should be calculated rather than guessed, what a bill of materials is, and a full worked calculation from order to order date – gross, net and lead time offsetting.
Back to the episode Arrow keys or swipe
What this covers
- The insight the whole method rests on
- The three inputs
- The bill of materials, and what an explosion is
- A calculation from start to finish
- Working backwards from the delivery date
- Lot sizing, and why you rarely order the exact requirement
- From MRP to MRP II to ERP
What this covers (cont.)
- What the method cannot do
The insight it all rests on
Before MRP, most factories managed component stock the way a shop manages its shelves: look at consumption, work out an average, reorder when the level falls below a reorder point.
Two kinds of demand, two completely different methods
Independent
Must be forecast
- The finished goods the customer buys
- Nobody can know for certain how many will sell
- You build an estimate from history and the market
- Example: how many bookcases will we sell in week 8?
Dependent
Should be calculated
- The components that go into the finished goods
- The requirement follows from the plan with certainty
- Forecasting it throws away information you already have
- Example: 100 bookcases require exactly 400 shelves
The three inputs
MRP is not a mystery. It is a calculator with three inputs, and the answer can never be better than those three.
What the calculation needs
- The production scheduleWhat is to be finished, how much, and in which week. The master production schedule.
- The bill of materialsWhat the finished item consists of, in what quantities, and at what levels.
- Inventory recordsWhat you already hold, what is on order, and the lead time for each item.
The bill of materials, and what an explosion is
The bill of materials is the recipe, but with levels. A bookcase consists of parts, and some of those parts consist of other parts.
Bill of materials for one bookcase
| Level | Item | Quantity | Lead time |
|---|---|---|---|
| 0 | Bookcase (assembled) | 1 | 1 week |
| 1 | Side panel (made in-house) | 2 | 2 weeks |
| 2 | Board (bought in) | 1 per side panel | 3 weeks |
| 1 | Shelf (bought in) | 4 | 2 weeks |
| 1 | Screw (bought in) | 24 | 1 week |
The calculation, from start to finish
Now we do the whole thing. 100 bookcases are to be delivered in week 8. In stock you have 20 side panels, 50 shelves and 1,000 screws. No boards.
The full calculation
| Item | Gross | In stock | Net | Needed week | Ordered week |
|---|---|---|---|---|---|
| Bookcase | 100 | 0 | 100 | 8 | 7 |
| Side panel | 200 | 20 | 180 | 7 | 5 |
| Board | 180 | 0 | 180 | 5 | 2 |
| Shelf | 400 | 50 | 350 | 7 | 5 |
| Screw | 2400 | 1000 | 1400 | 7 | 6 |
The answer, and why it surprises
Look at the last column. The boards have to be ordered in week 2.
A delivery in week 8 is in practice decided in week 2.
The arithmetic: 3 weeks for the boards, plus 2 weeks to make the side panels, plus 1 week of assembly. Six weeks in total.
It is the longest path through the bill of materials that decides, not the sum of all the parts. The screws have a one-week lead time and are ordered in week 6 – they are never the problem.
The consequence: if a rush order arrives in week 5, delivering in week 8 is physically impossible, however hard anyone pushes. The answer is in the bill of materials, not in willingness to try.
And that is why MRP is more than a shopping list: it tells you which promises you can actually make.
Lot sizing
In the example we ordered the exact net requirement: 350 shelves, 1,400 screws. In reality you rarely do.
Why you deviate from the requirement
Order the exact requirement
Minimum inventory
- No surplus capital tied up
- No parts left sitting
- But: many small orders
- And: full price per unit
Order in lots
Fewer, larger orders
- Screws come in boxes of 500, not 1,400 loose
- Discounts at higher volumes
- Fewer changeovers in production
- But: more stock, and more tied-up capital
From MRP to MRP II to ERP
The method grew in two clear steps, and the names confuse because the letters look alike.
Three generations
- MRP – materialsOrlicky, 1960s and 70s. Answers what to order and when. Looks only at materials.
- MRP II – manufacturing resourcesOliver Wight, 1983. Brings in capacity, machines, people and money. Manufacturing Resource Planning – same initials, bigger question.
- ERP – the whole businessPlanning becomes one module among many, alongside finance, purchasing, sales and HR.
What the method cannot do
Finally the honest caveat, because MRP rests on two assumptions that are both untrue.
Two assumptions, and what they cost
| Assumption | Reality |
|---|---|
| Fixed lead time | Lead times vary with how busy things are. A workshop running full takes longer – but MRP uses the same number regardless. |
| Unlimited capacity | Classic MRP never asks whether the machine has time free. It produces the plan and does not notice that it is impossible. That is precisely what MRP II was meant to fix. |
What is worth taking with you
That component requirements should be calculated, not guessed. Forecasts belong at the outer edge of the chain, where the customer is.
Key points
- The core insight: component requirements should be calculated, not forecast.
- MRP needs three things – a production schedule, a bill of materials and inventory records.
- Explosion means multiplying your way down the bill of materials, level by level.
- Net requirement is gross requirement minus what you already hold.
Key points (cont.)
- Lead time offsetting means working backwards from the date the customer needs the goods.
- The longest path through the bill of materials decides how early you must start.
- MRP assumes fixed lead times and unlimited capacity. Both are untrue.
Questions this answers
- What is MRP?
- What is the difference between dependent and independent demand?
- What is a bill of materials, and what does exploding it mean?
- How do you calculate what to order?
- What is lead time offsetting?
- What is the difference between MRP, MRP II and ERP?
Questions this answers (cont.)
- What are the weaknesses of MRP?
Sources
- Joseph Orlicky – Material Requirements Planning: The New Way of Life in Production and Inventory Management (1975)
- Material requirements planning – overview article